JavaScript is Required
Accepted Projects Details
Showing Record(s) 1 to 100 of Total 289 Green Box -Projects where all Issues are resolved
S.No Project Name Agency-Department Description Of Projects
(As furnished by the applicant)
Estimated Investment(in Crores)
1 Gare Palma IV/4 Coal Mine  Ministry of Coal  Subsequent to de-allocation of coal blocks by Hon’ble Supreme Court of India in 2014, auction of this coal blocks was conducted by Nominated Authority appointed by the Ministry of Coal (GOI), New Delhi. Post Bidding, Gare Palma- IV/4 Coal block, has been allocated to M/s Hindalco Industries Limited (HIL) and Ministry of Coal issued a vesting order no. 104/16/2015/NA dated 23rd March 2015 in favour HIL. 370
2 Rohini OC  Coal India Limited  It is a Brown field coal mining project having capacity of 2.0 / 2.3 MTY. Capacity to be expanded to 3.0 / 3.3 MTY. The project is in Ranchi district
3 Jharkhand OC  Coal India Limited  It is an expansion in capacity of Jharkhand OC from 1 MTY to 2 MTY / 2.7 MTY.
4 Koyagudem OC II Project  The Singareni Collieries Company Limited  Koyagudem OC II Project is a completed project. Stage II clearance of forest land(231.84 HA) is required
5 Ghonsa OC  Coal India Limited  This is an existing Project. EC is required for additional land (including Forest land for which Stage - I FC has been secured). Capacity of the Project shall remain the same.
6 Nehariya UG Expn.  Coal India Limited  This is an Expansion of existing Underground mine with increased mechanization for enhancement of capacity from 0.36 MTY to 0.54 MTY
7 New Sethia Expansion OC  Coal India Limited  This is a brown field Project and is an expansion of New Sethia OC (Cap. 0.2 MTY), to mine out lower group of seam in the existing Area with ehancement in capacity from 0.2 to 0.5 MTY.
8 Parsa Coal Mine  Ministry of Coal  Proposed project is for mining of coal for Chhabra TPP, Kalisindh TPP & Suratgarh Supercritical TPP of Rajasthan Rajya Vidyut Utpadan Nigam Limited. Lease area is 12.52 Sq. Km. (1252.447 ha) and it is proposed to produce of 5 MTPA.
9 ARDHAGRAM COAL MINE  Ministry of Coal  THE ARDHAGRAM COAL MINE WAS VESTED TO M/S OCL IRON AND STEEL FOR THEIR CAPATIVE PLATN
10 Majra Coal Mine  Ministry of Coal  M/S Jaypee Cement Corporation Limited (JCCL) has been declared successful bidder for allocation of Majra Coal Mine for captive use of its coal in Cement Plan/ CPP. The vesting order (Ref No.:104/34/2015/NA dt. 30th September, 2015) has been issued to JCCL by Nominated Authrity (Ministry of Coal). 200
11 Marki Mangli -III Coal Mine  Ministry of Coal  Marki Mangli -III Coal has been successfully Vested on 14th April 2015 to M/s B S Ispat Ltd vide Vesting order No.104/6/2015/NA for 2x100 TPD Sponge Iron Plant and 11 MW Captive Power Plant. The Capacity of the Mine is 0.21 MTPA as per approved Mining Plan from Ministry of Coal.
12 BARJORA(NORTH) COAL MINE  Ministry of Coal  Barjora (North) Coal Mine which was previously held by M/s DVC Emta Coal Mines Limited, was under operation and mining activity was going on till its de-allocation by the order of Hon’ble Supreme Court of India in September,2014. Nominated Authority, Ministry of Coal(MoC), Govt. of India, conducted the allotment process of the de-allocated coal mines under schedule I as per the provisions of the Coal Mines (Special Provisions) , Second Ordinance ,2014 and the Coal Mines (Special Provisions) Rules 2014 and allotted the Barjora (North) Coal Mine to The West Bengal Power Development Corporation Limited(WBPDCL) vide Order No. 103/7/2015 /NA dated 31.03.2015.Hence from 00:00 hours of 01.04.2015, WBPDCL became the owner of the mine. The Barjora (North) coal mine in Barjora Coal field lies between latitudes 23° 25’ 55’’N and 23° 27’ 42’’N and Longitudes 87° 13’ 48’’E and 87° 15’ 36’’E and falls within the administrative jurisdiction of Barjora Police Station in the Bankura district of West Bengal. The area is covered by the survey of India Topo Sheet No. 73M/3 and 73M/7 on R.F.1:50,000. The nearest Railway station from Barjora Coal field is Durgapur at a distance of about 30 Km, located on the Howrah-Delhi Main line of Eastern Railway. Barjora block is connected to Durgapur by a metal road via Durgapur Barrage. An all-weather metalled road connecting Barjora (lying on the Durgapur-Bankura Highway) and Saltora passes almost along the North-Eastern boundary of the Barjora coal field. Barjora North Open Cast Coal Mine has a Quarry Excavation Area of 663 Ha, total Project Area 927.5 Ha and 336.4 Ha of forest land needs to be diverted. 385.15
13 UTKAL D & E  Ministry of Coal  Utkal D & E coal mines has been allotted to NALCO on 02.05.2016. For Utkal D coal mine many statutory clearances are already available. NALCO has got the permission from MoC to develop Utkal D in Phase I and Utkal D and E combined in Phase II. However the statutory clearances in respect of Utkal D may be transferred in Favour of NALCO for the same. 533
14 SITANALA COAL MINE  Ministry of Coal  Sitanala Coking Coal Block is a 0.3MT underground project working with Manual longwall with stowing (Jankowice Method).
15 Brinda and Sasai Coal Mine  Ministry of Coal  Brinda & Sasai is located in the northern part of the North Karanpura Coalfield and falls within the administrative jurisdiction of Chatra and Hazaribag districts of jharkhand state.The total leasehold area is 1377.62 Ha. 303.15
16 Dumri Coal Mine  Ministry of Coal  Dumri Coal mine is located in villages of Balia, Pagar, Tunda and Pandu under Keredari revenue Anchal of Hazaribag district in the state of Jharkhand. The coal mine was earmarked for non-regulated sector in the recently concluded coal block auction by Ministry of Coal, Government of India. Prior to the coal block auction, the coal mine was allocated to M/s Nilachal Iron & Power Ltd (NIPL) and M/s Bajrang Ispat (P) Ltd. The Mine has now been vested with Hindalco Industries Ltd vide vesting order no. 104/24/2015/NA dated 22nd April 2015. As per CMPDA, the mine is supposed to be in production from Dec 2018. 200
17 Parbatpur Central Coal Mine  Ministry of Coal  The project was allotted to Steel Authority of India Limited on 23.03.2016 by MoC, GOI.The project consist of an opencast and an underground mine of total planned production as per approved Mine Plan is 1.24MT.
18 PVK 5 INCLINE  The Singareni Collieries Company Limited  PVK 5 INCLINE : Location: Khammam District Telangana State. Linkage: Basket Linkage. This is Brown field project. 114.7
19 Detailed coal exploration in Rajbar A Block, Auranga Coalfield  Coal India Limited  Detailed coal exploration in Rajbar A Block, Auranga Coalfield, District - Latehar, Approximate area of block 15.74 Sq.Km., Approximate Forest area in the block 1.07 Sq.Km. Anticipated Meterage 46100 m. Work order issued on 15.01.2016. 41.49
20 Detailed coal exploration in Rajbar C (Eastern Part) Block, Auranga Coalfield  Coal India Limited  Detailed coal exploration in Rajbar C (Eastern Part) Block, Auranga Coalfield, District - Latehar, Approximate area of block 8.8 Sq.Km., Approximate Forest area in the block 7.09 Sq.Km. Anticipated Meterage 22000 m. Work order issued on 30.11.2015. 19.8
21 Land Acquisition for Mine 1 and Mine 1A  Neyveli Lignite Corporation  Land acquisition pending for the running Mines commissioned already for mine advancement.
22 KETKI UG MINE  Coal India Limited  Ketki UG is an ongoing project of SECL. Production capacity 0.42 MTY. EC exists for 0.42 MTY. Captal outley Rs 46.24 Crores. Linkage will be to misc. consumers. 46.24
23 Neyveli New Thermal Power Project (2 x 500 MW)  Neyveli Lignite Corporation  The existing TPS-I of 600 MW capacity at Neyveli is continuously in operation since 1961 and it has been decided to phase out the operation of the Units and to set up a 1000 MW Thermal Power Plant at Neyveli viz. Neyveli New Thermal Power Station (NNTPS) in its place. The proposal to implement the NNTPS project has been sanctioned by GoI and the project activities have commenced. Order has been placed on M/s BHEL for Steam Generator & Auxiliaries(NTA 1) Package and Turbine Generator Package (NTA 2). 5907.11
24 Expansion of Lignite Mine-1 (Lease area) and Expansion of Lignite Mine 1A (3.0 to 7.0 MTPA)  Neyveli Lignite Corporation  The proposal to implement the NNTPS project has been sanctioned by GoI and the project activities have commenced. The present proposal for expansion of Mine-I (Lease Area) and Mine-IA (3.0 MTPA 7.0 MTPA) is to feed NNTPS of higher capacity, besides to cater to the existing supply to TPS-I Expansion and to ST-CMS, the IPP. The reserves of Mine-I is proposed to be increased by annexing two blocks (H&I) located at the west of the existing Mine-I while the reserves in Mine-IA is proposed to be increased on the western side below the outside dump area and also annexing the areas on the eastern and north eastern sides of existing Mine-IA. The reserves available in Mine-I may not be sufficient to meet the fuel requirement for the balance life of TPS-I Expansion and NNTPS for the next 25 years and the shortfall will be met out of the surplus lignite available from Mine-IA. 1458.17
25 Adriyala Shaft Project  The Singareni Collieries Company Limited  Adriyala Shaft Project was approved by GoI with a rated capacity of 2.81 MT and sanctioned cost of Rs 1228.39 Crores. 1228.39
26 DURGAPUR OC  Coal India Limited  Durgapur OC is an ongoing project. PR approved in Feb. 2015. 916.24
27 MANIKPUR OC EXPN  Coal India Limited  Manikpur OC Expn is an ongoing project. Project Report approved in Dec. 2009. 321.5
28 Hingula Washery  Coal India Limited  Hingula washery project, with a capacity of 10 Mtpa, will be located at Balaram Opencast Project in Hingula Area with raw coal linkage from Hingula Opencast mine under Build-Operate-Maintain (BOM) concept. The washery is designed to produce two products viz. clean coal with target ash (monthly average) content of 33.5% & rejects. 321.96
29 IB-Valley Washery at Lakhanpur  Coal India Limited  Ib-Valley coal washery project, proposed to be setup under 1st Phase, will be located in Lakhanpur Area with raw coal linkage from Integrated Lakhanpur-Belpahar-Lilari OCP on Build-Operate-Maintain (BOM) concept. The throughput capacity of the washery will be 10 Mtpa of raw coal. The washery will be designed to produce two products viz. clean coal with target ash (monthly average) content of 33.5% & rejects. 336.9
30 Jagannath Washery  Coal India Limited  Jagannath washery project, with a capacity of 10 Mtpa has been planned at the Pit head of Bhubaneshwari OCP in Jagannath Area, with raw coal linkage from Bhubaneswari Opencast mine. This is planned to wash non-coking coal under Build-Operate-Maintain (BOM) concept. The washery is designed to produce two products viz. clean coal with target ash (monthly average) content of 33.5% & rejects. 265.35
31 Basundhara Washery  Coal India Limited  Basundhara coal washery project with a capacity of 10 Mtpa is proposed to be set up under 1st Phase, which will be located in Kulda OCP with raw coal linkage from the Kulda OC of Basundhara Area. This is planned to wash non-coking coal under Build-Operate-Maintain (BOM) concept. The washery will be designed to produce two products viz. clean coal with target ash (monthly average) content of 33.5% & rejects. 334.72
32 Brinda and Sasai Coal Mine  Ministry of Coal  Brinda and sasai are contiguous coal blocks are located in the northern part of north karanpura coal fields and mainly falls in the chatra district and partly in Hazaribag district of Jharkhand. Block is fully explored by CMPDI and planned to operate partly by opencast and partly by underground method. A river named Barki flows by the east require to be diverted from the area. 303.15
33 Karo Washery  Coal India Limited  Karo washery is a non coking coal washery, linked to Karo OC. It will be constructed under BOM concept.
34 Shankarpur OCP (Phase IV)  Coal India Limited  Shankerpur OC Phase-IV Project of Capacity: 0.80 Mty, (life: 6 years) lies in Kenda Area of ECL in Burdwan Distt. This was approved on 12-09-14. 9.59
35 Bhanora West OC Patch  Coal India Limited  Bhanora OC Patch Project of Capacity: 0.50 Mty, (life: 6 years) lies in Sripur Area of ECL in Burdwan Distt. 17.89
36 Konar washery  Coal India Limited  Konar washery has a capacity of 7 MTY. It will be constructed using BOM concept.
37 Bansara OC Patch  Coal India Limited  Bansara OC Patch Project of Capacity: 0.50 Mty, (life: 5 years) lies in Kunustoria Area of ECL in Burdwan Distt. The patch falls within the Bansara Deep Geological Block. Mine is located 20 Km east of Asansol. The scheme was approved by ECL Board on 20.12.2013 17.84
38 Dabor Ph-III OC  Coal India Limited  Dabor Phase-III OC Patch Project of Capacity: 1.50 Mty, (life: 7 years) lies in Salanpur Area of ECL in Burdwan Distt. This was approved on 28-07-14. Coal dispatch is linked with ECLs basket of coal.   18.17
39 SPV FOR RAIL INFRASTRUCTURE OF MCL  Coal India Limited  Joint Venture Company of MCL, IRCON & IDCO(Odisha) named Mahanadi Coal Railway Limited has been formed to create Rail Infrastructures in the State of Odisha.
40 Jharkhand OC  Coal India Limited  It is a completed project. 110.89
41 HALDIBARI UG (0.42 MTY)  Coal India Limited  Is an underground ongoing project. PR approved on 15.10.2003. Coal production started in Oct 2010. 47.59
42 Kumardhubi UG , Barmuri OC & Rajpura OC under cluster -2  Coal India Limited  Projects/mines Kumardhubi UG(0.1 MTY), Barmuri OC(0.5 MTY) & Rajpura OC(0.5 MTY) under EC cluster -2 located in Dhanbad dist of Jharkhand
43 MOITRA COAL MINE  Ministry of Coal  Moitra Coal Mine is a green field project, with lease area of 293.54 Hectares with approved Mining plan of 1.0 Mtpa.
44 Restructuring of Mine-I and Expansion of Mine-IA  Neyveli Lignite Corporation  The project proposal is for Restructuring of Mine-I and Expansion of Mine-IA. As suggested by EAC, Mine-I capacity will be maintained at 10.50 MTPA. Mine-IA will be expanded from 3.0 to 7.0 MTPA. At present, Mine-I caters the fuel need of TPS-I (600 MW) and TPS-I Expansion (420 MW). Mine-IA caters the fuel need of TAQA (250 MW – IPP) and for higher PLF operation of NLC Power plants. The above proposal is for meeting fuel requirement of Neyveli New Thermal Power Station (NNTPS) (1000 MW) which is under construction. TPS-I (600MW)will be withdrawn in stages oncommissioning of NNTPS – 1000 MW 1458.17
45 Tikak OCP  Coal India Limited  The project is an existing mine under operation from 1982, based on the project report prepared by CMPDIL in 1978 called Baragolai Hill Top OCP, with a total mineable reserve of 8.166 MT. Environment Clearance for 0.2 MT was approved in 1995. The project falls within 4 sq. mile mining lease and Namdang coal grant vested with Coal India from Nationalization Act.The project has applied for renewal of forestry clearance for 98.59 Ha for life up to 2023. 12
46 Tipong OCP  Coal India Limited  Date of sanction 13-05-2011 Sanctioned Mine Capacity 1.00 MTY Sanctioned Capital Rs.260.15 Cr. (Outsourcing) Rs.683.27 Cr (Departmental) Mineable Reserve 19.03 MT Life 25 years Average Stripping Ratio 15.77 Cum/T Land 783.69 Ha (Forest) Scheduled date of completion 6th Yr. Anticipated date of completion-under Clearance Stage 1st year of production as per PR 4th Yr. of achieving targeted production 6th Yr. Actual date of production Not yet started. Previous UG working exists. Forestry Clearance applied. 260.15
47 Tirap OCP  Coal India Limited  A Project Report for Tirap OCP (0.6 MTY) prepared by CMPDIL was approved by Empowered Sub-Committee of Coal India Ltd. Board in its 68th meeting held on 10-07-2008, with total capital investment of Rs. 49.71 Crores (outsourcing option). The planned project is an extension of the existing project. However due to non-acquisition of land for external OB dump, the dump was relocated on a piece of Govt. land due to which the PR was recast in 2014, with Rs. 105.06 Crores investment (outsourcing option). The project involves land acquisition of 227 Ha. Govt. land for external OB dump and 289 Ha Forest land for mining. Applications for both was submitted in 2009 & 2008 respectively. 105.06
48 DHANPURI OC  Coal India Limited  DHANPURI OC is a completed project located in Shahdol district of MP.
49 Marki Barka (East)  Coal India Limited  Marki Barka (E) Coal Block is in Main Basin of Singrauli Coalfield located in North Cluster of CIL Blocks in Main Basin. Detailed exploration is under progress. GR & PR is awaited.
50 Marki Barka (West)  Coal India Limited  Marki Barka West Coal Block is in Main Basin of Singrauli Coalfield located in North Cluster of CIL Blocks in Main Basin. Part GR in non-forest area has been prepared by CMPDI and detailed exploration in balance area is under progress. Complete GR & PR is awaited.
51 Patpaharia  Coal India Limited  Patpaharia Coal Block is in Man Basin of Singrauli Coalfield adjacent to Dongrital Block. Detailed exploration has been done in non-forest area, however, it is required for forest area also for preparation of Project Report.
52 MAORI UG  Coal India Limited  It is Cost Plus project. Cost plus agreement yet to be finalized with prospective consumer. Date of Approval - 23.10.2008, Reserve - 8.831 MT(as on 01.04.2008), Life - 16 years Grade - G 8 74.8054
53 Chhattarpur - II UG Mine  Coal India Limited  Completed project contributing to 1 BT coal production (2019-20), Date of Recast of PR - January 1994, Reserve - 5.24 MT, Life - 31 years, Grade - G-7 (ROM) 16.35
54 Bhakra Underground  Coal India Limited  Green Field Project, Total Reserve - 3.3 Mte. Date of Approval - October 2008 on Cost Plus Basis, Life - 13 Years, Grade - B/C and Washery Grade - II, WCL Board in its 216 meeting held on 4.2.2009 accorded permission for starting mine development activities including land acquisition. 55.27
55 Dhankasa Underground  Coal India Limited  Green Field Underground Project, Total Reserve - 17.71 Mte. Grade - G 7, Life - 20 years,Date of Approval of PR-June 2008 on COST PLUS Basis. Project proposed to be worked through MDO route. MAHAGENCO & MPPGCL principally agreed for taking Coal on Cost Plus Basis. Cost Plus Agreement yet to be finalized. WCL Board held on 22/02/2014 accorded permission for starting the mine development activities and land acquisition as an ADVANCE ACTION. 153
56 Baranj I to IV, Manoradeep & Kiloni  Ministry of Coal  Mining operation in Baranj I to IV, Manoradeep and Kiloni COal blocks in chandrapur allotted to Karnataka Power COrporation Limited by Nominated Authority, Ministry of COal Govt. of Inida.
57 SIAL GHOGRI COAL MINE  Ministry of Coal  SIAL GHOGRI COAL MINE WAS ALLOTTED TO RELIANCE CEMENT COMPANY LIMITED PURSUANT TO WINNING THE BID HELD ON 14 FEBRUARY 2015 VIDE VESTING ORDER NUMBER 104/1/2015/NA DATED MARCH 23, 2015. 32.5
58 Chandragupt (Pachra) OC  Coal India Limited  It is a greenfield open cast coal mining project. It is located in Hazaribag district.
59 Sanghmitra OC  Coal India Limited  It is a greenfield open cast coal mining project. It is located in Chatra and Latehar districts.
60 Mandla South Coal Block  Ministry of Coal  Its an Under Ground Project having an area of 560 Ha having total extractable reserve of approx 13.37 MT. This Block has been e-auction to Jaypee Cement Corporation Limited for Captive use. This is located at a distance of around 25 Kilometers from Chhindawara.
61 Mandla North Coal Mine  Ministry of Coal  Mandla North Coal Mine allocated to Jaiprakash Associated Limited having 84 MT Extractable Reserves with 1041.60 Ha. of area is Underground Project. Coal will be extracted with deployment of Continuous Miner through Board & Pillar method. 500
62 Ghusick UG+OC  Coal India Limited  The Ghusik UG/OC Project is located in Burdhwan District of WB under administrative control of Sripur Area of ECL. It is about 6 Km from Asansol Rly Station. Production from this project is planned from 2019-20
63 Itapara OCP  Coal India Limited  Itapara OC is located in Raniganj Coalfield under administrative control of Salanpur Area of ECL.This Itapara Block lies in the east of Mohanpur Block. No colliery is at present running within within this block.The Block is at about 12 km due north from Asansol Railway Station.
64 Ganeshpur Coal Mine  Ministry of Coal  Ganeshpur Coal Block won by GMR Chhattisgarh Energy Ltd via recent Coal Auction Process conducted by Ministry of Coal, Government of India. MoC has issued the Vesting order dated 22ND April, 2015 to M/s GMR Chhattisgarh Energy Ltd.
65 Dongrital  Coal India Limited  First Underground Mine proposed in Singrauli Coalfield. Extractable reserves considered - 22.30 Mt. It is one of the 11 Coal Blocks in Main basin of Singrauli Coalfield, out of total 119 coal blocks retained with Coal India Ltd. Project report is based on Part GR on non-forest area. Permission for exploration in forest area is pending with MoEF. 715.16
66 Mohanpur Expansion OCP  Coal India Limited  The Mohanpur Expansion OC Project is under Salanpur Area of ECL in Barddhwan district of WB.It is located at a distance of 15 KM northward off GT Road from Burnpur Road Junction of Asansol Town. PR was approved in June-2008. 14.23
67 Waghoda UG  Coal India Limited  GREENFIELD OPENCAST PROJECT. > TOTAL RESERVES : 18.65 MT > EC exists for 0.39 Mty > GRADE OF COAL : G-8 > LIFE OF PROJECT : 48 71.73
68 Harradol UG  Coal India Limited  GREENFIELD UG PROJECT. > TOTAL RESERVES : 0.57 MT > SANCTION DATE : 10/08 subject to cost plus > EC exists for 0.135 Mty > GRADE OF COAL : WG-III > LIFE OF PROJECT : 6 16.36
69 Tawa III UG  Coal India Limited  GREENFIELD OPENCAST PROJECT. > TOTAL RESERVES : 6.863 MT > EC for 0.60 Mty recommended for grant of EC subject to submission of Stage - I FC. Stage - I FC awaited. > LIFE OF PROJECT : 13 105.69
70 Sharada UG  Coal India Limited  GREEN FIELD UG PROJECT. > TOTAL RESERVES : 7.54 MT > EC exists for 0.315 Mty > GRADE OF COAL : G-11 > LIFE OF PROJECT : 28 50.95
71 Dau North UG  Coal India Limited  GREENFIELD UG PROJECT. > TOTAL RESERVES : 2.074 MT > EC for Extension of Nandan - II (In Dhau North Block) applied. TOR Received. > GRADE OF COAL : WG III - G7 > LIFE OF PROJECT : 07
72 JAMUNIA UG  Coal India Limited  GREENFIELD UG PROJECT. > TOTAL RESERVES : 17.5 MT > EEC exists for 0.828 Mty in Non - Forest Land. EC for toatl land recommened subject to submission of Stage - I FC for the forest land. Stage - I FC awaited. > GRADE OF COAL : G-6 > LIFE OF PROJECT : 26 198.7627
73 Ukni Deep OC  Coal India Limited  BWORN FIELD OPENCAST PROJECT. > TOTAL RESERVES : 24.37 MT > SANCTION DATE : APR 2010 SUBJECT TO COST PLUS. HOWEVER COST PLUS CSA FOR PART QUANTITY PENDING FOR WANT OF CUSTOMER. > EC EXISTS FOR 3.5 MTY > GRADE OF COAL : G-9 > STRIPPING RATIO : 8.9 CUM/TE > LIFE OF PROJECT : 13 319.97
74 Pimpalgaon Deep OCM  Coal India Limited  Brown field project. PR under preparation. However PR is not viable on notified price and falling under cost plus category. 444.7
75 Bellora - Naigaon Deep OC  Coal India Limited  BROWN FIELD OPENCAST PROJECT ON COST PLUS BASIS. > TOTAL RESERVES : 16.68 MT > EC Exists - 1.25 Mty > GRADE OF COAL : G9 > STRIPPING RATIO :6.17 CUM/TE > LIFE OF PROJECT : 21 Final Approval of PR is pending for Finalization of CSA under cost plus basis by the consumer ie., M/s SWPL. 114.41
76 Bicharpur Coal Mine  Ministry of Coal  Bicharpur Coal Mine is located in Shahdol district of MP. Prior Allocatte was MP State Mining Corporation Block area 500 Hectare out of which mining lease was executed by previous allocate for 389.19 Hectare and 110.81 Hectare was in process of Stage 2 Forest Clearance. Being underground mine, prior allote obtained mine opening permission on 24.04.2014 and then initiated the development activity such as inclined and ventilation shaft drivage. About 6% of total development work was done before mine discontinued its operation on 24.09.2014 following Honourable SC Order. it would take at least 2 years time for completion of drivage / sinking and equipping it with required infrastructures from the commencement of work after new mining lease execution. Further, it would take another 3 years to reach its peak annual capacity of 0.75 MT which is as per approved mining plan schedule.
77 NORTH TISRA AND SOUTH TISRA EXPANSION OCP (6MTY)  Coal India Limited  The Project is an opencast coal mine for the exploitation of coal by Opencast method from I, II, III, IVT&B, V/VI/VII, VIII, VIIIA and IX/X seams of NT-ST OC mine. The capacity and capital cost of the project are 6.0 MTY and Rs. 555.52/- Crores respectively approved by BCCL/CIL Board to be worked by outsourcing. 555.52
78 MOONIDIH XV SEAM UG  Coal India Limited  The Project is a U/G coal mine for the exploitation of coal by Mass Production Technology from XV seam of MOONIDIH UG mine. The capacity and capital cost of the project are 2.5 MTY (22.5 MT during commercial production period of 9 years) and Rs. 1230.274/- Crores respectively approved by BCCL/CIL Board to be worked by MDO operator M/s INDU-SCCL-CGME Consortium. 1230.274
79 Kapuria UG (PSLW)  Coal India Limited  The Project is a U/G coal mine for the exploitation of coal by Mass Production Technology from L-5, XVI-C, XVI-A and XV seams of Kapuria Project. The capacity and capital cost of the project are 2 MTY (20.024 MT during commercial production period of 9 years) and Rs. 988.354/- Crores respectively approved by BCCL/CIL Board to be worked by MDO operator M/s AMR-BBB Consortium. 988.354
80 Talabira - 1, Coal Block  Ministry of Coal  Talabira - 1 Coal Block won by GMR Chhattisgarh Energy Ltd via recent Coal Auction Process conducted by Ministry of Coal, Government of India. MoC has also issued the Vesting order dated 23rd March, 2015 to M/s GMR Chhattisgarh Energy Ltd.
81 Gare Palma IV/7 Coal Mine - Monnet Ispat & Energy Ltd  Ministry of Coal  Monnet Ispat & Energy Ltd is the successful bidder of Gare Palma IV/7 coal mine has been issued vesting order on 23.03.2015. Gare Palma IV/7 Coal Block is an operation coal block under schedule II coal blocks and prior allottee is sarda energy & minerals Ltd. As per the vesting order clearances/approvals are to be transferred/obtained in the name of Monnet Ispat & Energy Ltd for continuation of Mining Operations.
82 BATURA (HW)  Coal India Limited  Batura (High Wall) Project is a Future project of 1 BT production programme. 231.52
83 MALACHUA OC  Coal India Limited  Malachua OC Project (3 MTY) is a Future project of 1 BT production programme
84 VIJAYWEST OC  Coal India Limited  Vijaywest OC Project (3.0 MTY) is a Future project of 1 BT production programme. 843.06
85 RAI OC  Coal India Limited  Rai OC Project (15 MTY) is a Future project of 1 BT production programme
86 MADANNAGAR OC  Coal India Limited  Madannagar OC Project (12 MTY) is a Future project of 1 BT production programme 1875.32
87 AMBIKA OC  Coal India Limited  Ambika OC Project (1.0 MTY) is a Greenfield project located in Korba District. The project approved in Jun. 2006 by SECL Board. Total capital outlay is Rs. 22.30 Crores 22.3
88 Kolarpimpri Extn OC  Coal India Limited  BROWN FIELD OPENCAST PROJECT. > TOTAL RESERVES : 35.317 MT > SANCTION DATE : YET TO APPROVED ON COST PLUS BASIS > EC EXISTS FOR 1.5 MTY > GRADE OF COAL : G-9 > STRIPPING RATIO : 7.463 CUM/TE > LIFE OF PROJECT : 25 YEARS 466.8545
89 Block-B Expansion  Coal India Limited  Brownfield Project for expansion of coal production from 3.5 Mty to 8 Mty (PR for Expansion under preparation by CMPDI).
90 Bina-Kakri Amalgamation OCP (10 Mty)  Coal India Limited  Brownfield Project with balance reserves of Bina Extension OCP (6 Mty) and reserves in dip side of Bina Extension and Kakri OCPs. Dip side area falls in Singrauli district of MP. Evacuation through Rail. 746.04
91 Junaad Extn OC  Coal India Limited  BROWN FIELD OPENCAST PROJECT. > TOTAL RESERVES : 3.92 MT > Project is in operation within the land in possession with CSA on cost plus basis with Mahagenco. However PR requires updation considering enhanced land rates and finalization of amendments in CSA with Mahagenco. > EC EXISTS FOR 0.6 MTY > GRADE OF COAL : G-9 > STRIPPING RATIO : 8.26 CUM/TE > LIFE OF PROJECT : 11
92 Amelia (North) Coal Mine  Ministry of Coal  Amelia (North) Coal Mine is an Open Cast Coal Mine having 70 million tones of extractable reserves. This is a part of Singrauli Coal Fields situated at Village Amelia, Tehsil/Taluka/District Singrauli, Madhya Pradesh. This project has already developed CHP and Wagon Loading arrangment.
93 Mungoli-Nirguda Deep Extn OC  Coal India Limited  BROWN FIELD OPENCAST PROJECT. > TOTAL RESERVES : 38.60 MT > SANCTION DATE : PR APPROVED ON COST PLUS BASIS HOWEVER PR IS UNDER REVISION AT CMPDI FOR BRINGING THE PROJECT OUT OF COST PLUS AMBIT. > EC FOR CAPACITY OF 3 MTY TO BE OBTAINED: TOR received dated 30.9.2014. TL - March 2018 > GRADE OF COAL : G-9 > STRIPPING RATIO : 6.40 CUM/TE > LIFE OF PROJECT : 17 372.5193
94 Jayant Expansion OCP ( 10 to 20 Mtpa)  Coal India Limited  This is brown field project for expansion of 10 to 20 MTY coal production. Coal evacuation is proposed through MGR of NTPC and through railway to UPRVUNL. 1226.38
95 Amalgamated Yekona I & Yekona II OCM  Coal India Limited  GREENFIELD OPENCAST PROJECT. > TOTAL RESERVES : 57.85 MT > SANCTION DATE : 03/02/2015 > EC exists for Yekonal -I -0.40 Mty & 0.60 Mty for Yekona -II . Fresh EC is to be obtained for 2.5 Mty after approval of PR. TL- Marach 2018 > GRADE OF COAL : G-8 > STRIPPING RATIO : 7.82 CUM/TE > LIFE OF PROJECT : 23 828.741
96 Introduction of 2nd CM at Jhanjra UG Mine  Coal India Limited  Located in the north-eastern part of Raniganj Coalfield under administrative control of Jhanjra Area. Commissioning and start of production from Continuous Miner - II set were done in May 2014. 112.23
97 New Majri UG to OC project  Coal India Limited  BROWN FIELD OPENCAST PROJECT. > TOTAL RESERVES : 12 MT > EC EXISTS FOR 0.8 MTY > GRADE OF COAL : G-11 > STRIPPING RATIO : 3.59 CUM/TE > LIFE OF PROJECT : 19 The Project is a cost plus project under agreement with MAHAGENCO. However, PR required updation in view of enhanced land rates and other cost indices. The PR has been updated and requested Mahagenco for revision in pricing clauses of cost plus FSA. Mahgencos consent for finalization of agreement is awaited. 72.57
98 Nerad Malegaon coal mine  Ministry of Coal  Nerad Malegaon coal mine is a combination of OC+UG mine with peak rated capacity as under: 0.15 MTPA (OC) + 0.21 MTPA (UG)
99 Brahmani-Chichropatsimal  Coal India Limited  This virgin block lies in Brahmani Basin in Dumka district of Jharkhand State.Production from this block is planned in 2019-20.
100 Chaidhar Gariapani  Coal India Limited  This virgin block lies in Mahuagarhi Basin in Godda District of Jharkhand. Production from this block is planned from 2018-2019.
next last
Go to Navigation